Pennsylvania Farm Bill Conservation Programs Calendar
Last Updated
March 5, 2008
March 2008
Field offices should emphasize developing conservation plans with high priority
farmers and landowners. Send requests for I&E assistance to Area Offices.
March 15, 2008- Extension of 2002 Farm Bill expires. Authority
expires for CRP, FRPP, GRP, WHIP and WRP.
Obligate all 2008 FRPP, WHIP and WRP funds.
April 2008
April 1, 2008- Field Offices receive list from Farm Service Agency of Prior Year
CRP contracts selected for status review.
July 2008
July 1, 2008- Finish
obligating 2008 AMA funds.
August 2008
August 29, 2008- Applications filed for first ranking cycle
for FY 2009 AMA, EQIP, WHIP, and WRP. Also state CIG, if allowed.
September 2008
September 12, 2008 - Complete all FY 2008 payment approvals and contract
modifications in Protracts in preparation for end-of-year closeout.
September 30, 2008- Applications filed for consideration in
second ranking cycle for FY 2009 AMA, EQIP, WHIP, and WRP funding. (A second
ranking will only be done if funds remain after first ranking period.)
October 2008
October 11, 2008- Finish ranking
applications received by August 29, 2008 for the first ranking period.
November 2008
November 1, 2008- Field offices begin sending reminder letters
to program participants with practices scheduled for fiscal or calendar year
2009.
Applications
received in the second round by September 30, 2008 are ranked (if funding was
available).
November 28, 2008-
Applications approved for funding from the first ranking period are obligated.
December 2008
December 19-
All funds are obligated for FY 2009 AMA, EQIP, WHIP, WRP, and state CIG.
December 31, 2008-
Field offices finish contract reviews for program participants who are out of
compliance.
|